The CM method was chosen in order to ensure transparency in the flow of construction costs, to reliably deliver strict construction process management of subsidy funding and development and land formation works and other aspects, and to guarantee the quality of class 100 clean rooms etc. We handled design supervision of the architectural design, basic design of the structure and services, and CM of the design for execution and construction works. The design for execution, supervision, and construction works were ordered as a batch from a major construction company selected by the comprehensive evaluation method. Ordering the development and land formation works and the design for execution simultaneously from a construction company made it possible to start on the development and land formation works during the design for execution period, shortening the construction period. Construction costs for design changes were handled with proposals for VE etc., so the construction was completed with no cost changes.
Approach
Award
CM Award 2013